Tile, Appliances, Countertops, and More

Dear Praying Friend,
Thank you for your interest in our parsonage project. Even though our men were able to take some much-needed rest over the holidays, several important projects were completed:
- Tile both upstairs bathrooms was completed.
- Appliances arrived and were set in place.
- Countertops arrived early and have been installed.
- Four-way inspection for the finished basement was passed!
As you remember our project, please be in prayer for the following items:
- A large work-team is scheduled to begin January 23. Please pray for their travel arrangements, safety, and overall effectiveness. We are very grateful for their willingness to chip in and are eager to fellowship with them.
- Continued financial contributions so that our construction loan could be as low as possible.
By God’s grace, we’re still on track for a March 1 completion date, but a lot has to get done between now and then. We covet your prayers.
Yours in Christ,Pastor Greg Baker